Spain ties data-centre grid access to hourly renewables
Spain's new data-centre decree entered into force on 22.11.2026, setting a standard minimum 80% hourly renewable-electricity requirement for covered centres.
Covered data-centre operators must demonstrate compliance; annual certificate volumes alone do not prove hourly matching. Suppliers structuring qualifying renewable-electricity purchase contracts for these buyers will need eligible generation and a contract term of at least six years.
Royal Decree 1032/2026 was published on 21.11.2026. Its grid-access requirements cover centres with access capacity of at least 10 MW, including same-owner centres at one location that together reach the threshold.
The scope includes pending applications and permits already granted where centres are not yet connected.
Pending applications generally have three months from entry into force to demonstrate compliance. Projects with permits already granted but not yet connected generally have six months, subject to the decree's exceptions.
Hourly matching and asset eligibility
Hourly matching means backing consumption with renewable electricity generated in the same hour, allowing for storage under the decree's accounting provisions. Renewable generation must also meet additionality conditions, generally linked to a commissioning window of 36 months before the centre starts operating or first uses the electricity concerned.
Specified photovoltaic, biomass and repowering cases have separate eligibility rules. The exceptions do not make every existing plant eligible.
The owner of the generating installation associated with qualifying long-term renewable-electricity purchase contracts must redeem the associated guarantees of origin (GOs) at least annually, identifying the data centre's electricity supply point by its CUPS code. Those certificates remain part of the evidence chain, but annual GO volumes alone do not prove hourly matching.
The decree does not establish a GO price premium.
Shortfalls in additionality or hourly matching trigger compensation charges, separate from any applicable sanctions.
Transition offers lower hourly thresholds
Qualifying centres that meet automatic power-reduction requirements can use an alternative hourly-matching route during a five-year transition starting on 22.11.2026. This route does not remove additionality requirements.
Until 31.12.2028, the renewable threshold is 60% in each P1 peak-period hour. From 01.01.2029, it rises to 70% in P1 hours, with 60% required in P2 mid-peak hours, for the rest of the transition.
The route includes priority power reduction. Only centres entering operation before 31.12.2030 can qualify, but the shared five-year transition runs into November 2031; each centre does not receive its own five-year period.
Separate regime for a renewable share above 90%
A separate compliance route applies when Spain's renewable-generation share exceeded 90% in the calendar year two years before the application year. It requires an official determination and caps annual hours drawing electricity from the grid; it is not an automatic end to the rules.
Data4 supply agreement dates from 2025
TotalEnergies announced on 04.11.2025 a ten-year agreement to supply Data4's Spanish sites from January 2026. The contract covers 610 GWh in total from Spanish wind and solar farms with capacity equivalent to 30 MW.
The announcement does not establish whether particular Data4 sites fall within the decree or whether the agreement meets its requirements.